Permit A1618913 is in the Inspections phase as of 6/5/2026.
You’ve got your permit and may begin working. Please contact the Building Inspection unit to schedule an inspection and keep your project on track!
- Intake and PaymentTarget duration:
1–2 Business Days - Project ReviewTarget duration:
30 Business Days - Zoning AppealTarget duration:
60–90 days - Issuance
- InspectionStarted on:
7/8/2024 - OccupancyStarted on:
Not yet started - Completed
About this Permit
Amendment to a Long Form
25 BENTLEY ST
Brighton, MA 02135