Permit SF1786848 is in the Inspections phase as of 5/30/2026.
You’ve got your permit and may begin working. Please contact the Building Inspection unit to schedule an inspection and keep your project on track!
- Intake and PaymentTarget duration:
1–2 Business Days - Project ReviewTarget duration:
30 Business Days - Zoning AppealTarget duration:
60–90 days - Issuance
- InspectionStarted on:
10/23/2025 - OccupancyStarted on:
Not yet started - Completed
About this Permit
Short Form Bldg Permit
116 SUTHERLAND RD
Brighton, MA 02135