Permit SF1860793 is in the Intake & Payment phase as of 6/24/2026.

Thanks for your application! Staff is reviewing your application to ensure that all fees are properly calculated and we have the information needed to start processing it.

  • Intake and Payment
    Target duration:
    1–2 Business Days
    Started on:
    6/17/2026
  • Project Review
    Target duration:
    30 Business Days
    Started on:
    Not yet started
  • Zoning Appeal
    Target duration:
    60–90 days
    Started on:
    Not yet started
  • Issuance
    Started on:
    Not yet started
  • Inspection
    Started on:
    Not yet started
  • Occupancy
    Started on:
    Not yet started
  • Completed

About this Permit

Short Form Bldg Permit
2 ROLLINS ST
Roxbury, MA 02118

Open reviews

  • Inspection Review
  • Parks Commission Review

Have questions?

Call 617-635-5300 and ask for ISD Counter 1.